Composite Deck Build
All Projects

Composite Deck Build

A 520 sq ft composite deck with cable railing and integrated bench seating off the back of the house.

Manteca, CA3 weeks$29,800
Scope of work

What we did.

  • Concrete pier footings and pressure-treated substructure
  • Composite decking with hidden fasteners
  • Cable railing system with metal posts
  • Built-in bench and step lighting
Materials used
Decking
Capped composite, 25-year warranty
Substructure
Pressure-treated Douglas fir on concrete piers
Railing
Powder-coated aluminum posts with stainless cable
Photo gallery

The build, start to finish.

Finished deck and railing
Finished deck and railing
Decking and bench detail
Decking and bench detail
Timeline

3 weeks, phase by phase.

  1. Week 1
    Layout & footings

    Permit, layout, pier holes, inspection, pour.

  2. Week 2
    Framing

    Ledger, beams, joists, blocking.

  3. Week 3
    Decking & rail

    Boards, railing, bench, lighting, final.

Budget breakdown

Where the $29,800 went.

Decking material34%
Composite boards and fasteners
Labor30%
Framing through finish
Railing18%
Cable system and posts
Substructure12%
Footings and PT framing
Lighting & permits6%
Step lights, city permit

Percentages are approximate and specific to this project. Every estimate from Chadha Construction is itemized in writing before work begins.