Driveway Concrete Pour
All Projects

Driveway Concrete Pour

Removed a cracked, settling driveway and replaced it with a reinforced broom-finish slab and new approach.

Salida, CA2 weeks$18,400
Scope of work

What we did.

  • Demo and haul-away of the old slab
  • Base prep and compaction
  • Rebar reinforcement and control joints
  • Broom finish with sealed edges
Materials used
Concrete
3500 PSI ready-mix with fiber mesh
Reinforcement
#4 rebar on 18" grid
Finish
Medium broom with tooled control joints
Photo gallery

The build, start to finish.

Finished driveway
Finished driveway
Forms and rebar before pour
Forms and rebar before pour
Timeline

2 weeks, phase by phase.

  1. Week 1
    Demo & base

    Old slab removed, base graded and compacted.

  2. Week 2
    Forms & pour

    Rebar, forms, pour, finish, cure and seal.

Budget breakdown

Where the $18,400 went.

Concrete & rebar40%
Ready-mix and reinforcement
Labor34%
Demo, prep, pour, finish
Base material14%
Class 2 base and compaction
Disposal & permits12%
Haul-away, city approach permit

Percentages are approximate and specific to this project. Every estimate from Chadha Construction is itemized in writing before work begins.